Marri Wind Farm

Alinta Energy is developing the Marri Wind Farm project in the Shire of Dandaragan, approximately 140 km north of Perth. 

project size

Project size: Up to 550 MW

turbines

Number of turbines: Up to 81

calendar icon with clock

Expected operating life: 30 years

TIMELINE

1
Landowner discussions and benefits

We're talking with landowners who are interested in the benefits of hosting a wind farm.

2
Environmental surveys

We're undertaking a range of technical, environmental and heritage investigations to inform the design of the wind farm (alongside consultation with key stakeholders).

We are here
3
Consultation
We are here

We'll be working closely with landowners, neighbours and key agencies. We are excited to get to know the wider community throughout the project.

4
Government approvals

We’re aiming to submit environmental approval and development applications to the Department of Water and Environmental Regulation and the Department of Planning, Lands and Heritage in 2025.

5
Final investment decision
6
Construction

We aim to start construction in 2026. Construction typically takes 18 months to 3 years.